July 2020 Update
July 2020 Update Phase 3, the build-out of office spaces, is well underway, and the additions to house stairs and an elevator are in place. There are glass walkways to
December 2019 Update
December 2019 Update We had a great deal to be thankful for on Thanksgiving Day. On the Wednesday prior, a three story portion of the north brick wall collapsed, and
September 2019 Update
September 2019 Update Our contracting partners at Lehman Daman came sliding into home base in plenty of time to deliver on our pledge to have the summer package of work
August 2019 Update
August 2019 Update Hot Times in This City The heat wave of 2019 couldn't slow things down! Our summer package of work, which includes the outside projects which must
June 2019 Renovations
June 2019 Renovations The Good Haus project has been phased to address both the immediate stabilization needs and a full renovation and expansion of the building. This month we will see a mitigation of